Architect & contractor coordination pack · Updated 16 August 2026

Home Automation
Pre-Wiring Checklist.

A printable coordination worksheet for Jaipur architects, interior designers, MEP teams, electrical contractors and automation integrators—before drawings freeze, conduits disappear or ceilings close.

Ask for a drawing review

Planning aid, not an electrical design certificate. Final cable sizing, protection, earthing, routing, life-safety interfaces and equipment selection must be approved by the responsible project professionals and applicable authorities. Manufacturer instructions take precedence.

The rule: decide outcomes, interfaces and responsibility before products. “Bedside all-off”, “arrival scene”, “gate-to-door video”, “internet-down operation” and “movie mode” become coordinated requirements only when they appear in drawings, schedules, interface matrices and test records.

Project record

Issue this sheet with a drawing revision.

Complete these fields before circulating the checklist. Use one status vocabulary throughout the project: required, not required, pending or approved.

Entries stay in this page only long enough to print or save the sheet. This form does not submit project data.

01

Before drawings freeze

New build or major renovation? A dedicated automation bus such as KNX twisted pair can be planned into the fabric of the building. A finished home may be better served by a carefully designed wireless or hybrid system. KNX officially supports twisted pair, RF and IP media; Matter uses IP networking over technologies including Wi-Fi, Ethernet and Thread.
02

Backbone, panels and network

03

Room and zone point schedule

Use drawing references, not informal room names alone. Add rows for every repeated bedroom, toilet, façade zone and external building. Write N/R where a discipline has confirmed that an interface is not required.

Room / drawing ref.LoadsKeypads / sensorsHVAC / shadingPower / network / busSecurity / AVTermination, fallback & status
Entrance / foyerFoyer and exterior groupsEntry keypad, door contactLock/intercom supply and dataDoor station, lock, cameraRack/DB refs; manual key; pending
Living roomAmbient, task and feature groupsEntry/scene keypad, occupancyAC interface, curtainsBus, data, TV and control powerDisplay, audio, camera if approvedPanel/rack refs; manual lighting
DiningTable, cove and feature lightingScene keypad, occupancyAC zone, curtains if anyBus/data provisionsAudio zonePanel ref; dining/cleaning scenes
Family loungeLighting and fan groupsScene keypadAC and shadingTV/data and busDisplay, audio, gamingRack ref; manual source recovery
Bedroom (repeat)Lighting, fan, bedside loadsEntry/bedside keypads, occupancyAC, curtains/blindsBus, data and chargingTV/audio if requiredAll-off excludes essentials
Study / home officeTask and general lightingKeypad, occupancyAC zone, blindsTwo data outlets, AP reviewVC display/audio if requiredNetwork/rack ref; work mode
KitchenTask, counter and general lightingManual control, leak inputExhaust interface if approvedAppliance circuits and data needsLeak/gas detection by specialistSafety devices remain independent
Bathroom (repeat)Mirror, general and exhaustApproved wet-area sensingExhaust run-onSuitable power and controlsEmergency pull if specifiedManual override; equipment rating
Utility / staff roomLighting and selected equipmentSimple local controlsVentilation if applicablePower/data as scheduledAccess policy if requiredRestricted scenes; labelled fallback
Stairs / corridorGeneral and low-level lightingPresence zones, two-way logicBus and emergency separationCamera only where approvedNight path; manual override
Balcony / terraceExterior lights and selected loadsWeather-suitable controls/sensorsAwning/shading if specifiedOutdoor power, data and conduitPerimeter sensor/cameraDrainage, enclosure and isolation
Parking / drivewayLighting, pumps if applicablePresence/daylight inputsOutdoor routes and backupCCTV, intercom, accessDB/rack refs; safe manual control
Plant / MEP roomApproved controllable plant onlyStatus/fault inputsManufacturer interfacesPanel, gateway and networkRestricted accessMEP approval; local plant controls
RoofLighting and approved equipmentEnvironmental inputs if requiredHeat/rain-rated routes and boxesCCTV or antenna provisionsIsolation, drainage and service access
Gatehouse / main gateGate/guard lightingGuard button, access inputsPower, data, spare conduit, backupGate motor, safety, CCTV, intercomManual release; egress; approved
 
 
04

CCTV, access and sliding gate

05

Home theatre and distributed AV

06

Drawing and schedule register

Assign an owner, revision and approval status to each deliverable. A checkbox without a matching drawing or schedule is not coordination.

DeliverableOwnerDrawing / revisionStatus / date
Reflected ceiling plan: luminaires, sensors, speakers, APs and cameras
Lighting control plan, load schedule and keypad schedule
ICT/ELV layout, containment plan and riser diagram
Automation panel SLD and panel GA
Network rack elevation, patching and PoE schedule
System interface and responsibility matrix
Scene / cause-and-effect matrix and fallback behaviour
Equipment, cable and termination schedule
Approved as-built issue and O&M index
07

Construction stage gates

08

Do not accept handover without these

Primary references

This checklist is practical field guidance. For system and regulatory decisions, consult the current project documents and standards directly: